Figure 1 A sketch of a typical three-phase oil-filled power transformer
The International Electrotechnical Commission (IEC) 60076-5, Standard for Power Transformers – Part 5: Ability to withstand short circuit
The Institute of Electrical and Electronic Engineers (IEEE) C57.12.00, Standard for General Requirements for Liquid-Immersed Distribution, Power and Regulating Transformers
The Institute of Electrical and Electronic Engineers (IEEE) C57.104, Guide for the Interpretation of Gases Generated in Oil-Immersed Transformers
Transformers are used to step up or down supply voltages. Essentially there are two types of transformer, dry & liquid immersed. A dry-type transformer is most suitable for indoor installation whilst liquid immersed type is suitable for both indoor & outdoor environments
Figure 2 A sketch plan of the windings of the three-phase oil-filled power transformer
In a typical oil-filled transformer, each of the three phase windings has four layers of winding coils: two are low-voltage (LV) comprising an inner and an outer coil, and two are high‑voltage (HV) comprising a main and a coarse regulation (CR) / fine regulation (FR) coil. Each of the coils comprises many turns of copper conductors that is wrapped with paper insulation. The LV coils are housed concentrically within the HV coils and wound onto a laminated sheet steel core.
Figure 3 The internal construction of a winding phase of the three-phase power transformer
There are insulating spacers separating each individual concentric layer of LV & HV coils, constructed in cylinder pressboard sheets, and supported by vertical strips from wood. The top & bottom of each winding are stacked with wooden blocks, and there are wooden structures compressing the blocks and the windings.
In most large transformers, there is an on-load tap changer (OLTC), whichautomatically regulates the voltage of the transformer in the event of load variation.
Are used in electricity transmission systems or at large commercial site, such as power plants & industrial plants, where there is a high demand for electricity. They are generally rated from 200MVA, with operating voltages starting at 33kV
The life expectancy of a power transformer is generally more than 20 years of service, working within conducive environments. However, unusual service conditions can reduce its life expectancy. For example, operating outside the normal ambient temperature range (-20°C & 40°C), installed at high altitude (> 1000 m above sea level) & seismic conditions.
The transformer may be fitted with a number of the following protection devices,
Step down voltage from electricity transmission systems to the level used by end-users. They are generally rated at not more than 200MVA, with operating voltages no more than 11kV
Figure 4 A sketch of a typical three-phase oil-filled distribution transformer
Are used in industrial processes running on direct current (dc) supply, such as dc traction, electrolysis, smelting operations & large variable speed drive trains. Power electronic circuits convert alternating current (ac) to dc, aka rectifier circuits. Power electronic circuits also convert dc to ac, aka inverter circuits. A transformer that has one of its windings connected to either a rectifier circuit or an inverter circuit is respectively known as a rectifier transformer or a converter transformer
Have dielectric of a gas or a solid on their windings; the windings are not immersed in an insulating liquid
(aka Steady-state reactive compensation & Current limiting reactors, respectively) Are used in electrical power systems to limit over-voltages or heavy/short-circuit current in power transmission
Shunt Reactors stabilize voltages during load variations. Long HV voltage transmission lines generate a substantial amount of leading reactive power when the supply lines are lightly loaded. Conversely, they absorb a large amount of lagging reactive power when the supply lines are heavily loaded. Without reactive power balancing, the rated voltage on the transmission lines cannot be maintained under load variations.
Series reactors protect against excessively large currents under short-circuit or transient conditions. Applications include motor starting and electric arc furnace (EAF)
Isolate the transmission systems or mains supply circuit with the control & measuring devices, by magnetically coupling both circuits. They step down hazardous voltages or currents to a safe level for measurement or monitoring. The instrument transformers comprised current transformers & voltage transformers
Couple high current lines with the monitoring devices. The primary winding of the CT is connected in series with the load current-carrying conductor. The secondary winding proportionally transforms the primary levels to typical values of 5 A for metering applications, such as wattmeters, power-factor (PF) meters, voltmeters, ammeters & relays
(aka Potential Transformers) Reduce hazardous high voltages to a level that can be safely applied to voltmeters or protective relays. The primary winding of the VT is connected in parallel with the monitored circuit. The secondary windings proportionally transform the primary levels to typical values of 120 V, for metering applications, such as wattmeters, power-factor (PF) meters, voltmeters, ammeters & relays
The purposes of investigating transformer failures are,
In addition to physical damage to the transformer and its resulting downtime, failures of transformers can lead to power interruption to the premises and significant business interruption losses.
Outline of the failure investigation:
Issues for Consideration
Recording & Notes
Document & photograph the investigation process, so that evidence that has been inevitably destroyed or tampered with during the course of the inspection is available for later assessment
Findings
Once the cause of the failure incident has been determined, further work may involve reviewing the current maintenance program and suggest recommendations, if any, to prevent a similar occurrence of the failure
A diagnostic technique for the detection of incipient fault conditions in oil-filled transformers, by interpreting the test results of the dielectric oil sampled from the transformer. Test results of the DGA for several years can assist in the trending of the failure mechanism of the equipment
The key gases of DGA are hydrogen (H2), methane (CH4), acetylene (C2H2), ethylene (C2H4), ethane (C2H6), carbon monoxide (CO) and carbon dioxide (CO2). With the exception of CO2, the remaining six gases are combustible. The followings are indicative signs of the individual gases,
Detects signs of oil deterioration including reduced dielectric strength, increased moisture & change in colour of the oil. For example,
- Reduced oil dielectric strength - possible contamination or
excessive water
- Increased moisture in oil - may be associated with excessive
water in the paper
Winding ratio that was different from the factory test record indicates electrical shorting of the winding. The shorting can occur between turns (aka inter-turn shorting) or between windings, such as disc-to-disc
Indicates the moisture and possible deposition of conductive dust particles on the surface of insulation material. Polarization index
< 2.0 indicates deterioration of the insulation
Detects winding problems including unintended movements caused by mechanical impact (for example, transportation) or electromotive force that was produced when supplying high current to an external short-circuit event
Detects for any localised dielectric breakdown or deposits of conductive dust particles on solid insulation of the windings
Tests the insulation between two windings, or between the windings & the earthed chassis
Evaluates any displacement of the transformer core, windings and the holding structures
Following the inspection of equipment on the site and collection of the background information, it is often necessary to inspect the internal windings of the transformer for any physical evidence of the failure. The process should be directed by a person having knowledge of the equipment. Untanking of the transformer windings is best undertaken in the manufacturer’s facility, where hoist equipment, tools for dismantling & test equipment are available to facilitate the inspection, and manufacturer’s engineers are available for discussion. Look for the following signs,
The steel cores are surrounded by the transformer windings and are laminated to reduce eddy-current. They concentrate the magnetic flux of the windings. Due to gaps, excessive burrs on the edges, poor maintenance or contaminated oil, the laminated steel cores can give rise to localised heating that reaches the surface, which then leads to a fault at the winding by direct contact. Signs to look for,
Winding tanks contained insulation oil, which acts primarily as an insulation medium & cooling for the windings. Leaks at the tank wall can occur due to corrosion, thermal cycling or weld cracks, resulting in the reduction of the oil level and the ingress of moisture. Insufficient cooling oil can lead to overheating of the windings
Occurrence of leaks can lead to the ingress of moisture, which reduces the dielectric strength of the insulation oil
Impediment to the flow of insulation oil reduces the cooling efficiency for the windings. Loss of cooling can also be associated with malfunctioning fan motors. As a result, the operating temperature of the transformer increases, which causes a corresponding decrease in the capacity of the equipment
The leading cause of transformer failure is the breakdown of electrical insulation of the windings, which can result from poor installation, inadequate maintenance, defective material or deteriorating insulation due to ageing or mechanical damage associated with vibration. Oil deterioration caused by conductive particles or moisture in the oil can initiate electrical dischargescracks, resulting in the reduction of the oil level and the ingress of moisture. Insufficient cooling oil can lead to overheating of the windings
High level of electromotive forces in the event of a short-circuiting fault at the load circuits can lead to movements in the winding turns. In some severe situations, the winding displaces or buckles, causing abrasion to the windings’ paper insulation to the extent that conductors are exposed. Subsequently, localised arc damage can occur at one or more points of the winding turns
Are insulating devices that allow an electrical conductor to pass safely through the grounded winding tank of the transformer. Common mechanisms that lead to bushing failures include leaks, projectiles and defective porcelain or polymer insulator. Problems of thermal instability in bushings can result in separation of seals. Deteriorated seals in terminal connections can lead to the ingress of moisture, which permeates into the oil & paper insulation, degrading the dielectric medium. Projectiles can shatter porcelain sheds
Originate from external sources. Overvoltages produced by lightning activity are more significant in the vicinity thunderstorms. Overvoltages in the transmission lines are transients associated with switching operations at the power station
Regulate voltage levels of the transformer by either adding or removing turns from the secondary winding, thus, maintaining the desired voltage at varying loads. Problems associated with LTCs include misalignment of contacts, poor design of the contacts, high loading and component failures, which include failures of springs, bearings, shafts & drive mechanisms. Excessive wearing can cause contact failure
Copyright © 2018 efe Consultants Pte Ltd | Privacy Policy